This project consists of replacing approximately 750 ft of combined sewer and installing approximately 900 ft of storm sewer on Brookside Boulevard west of West 130 Street.
Project start date: Oct 2, 2023
APRIL 12, 2024
PROJECT UPDATE: On Thursday, April 18, 2024, work on Brookside Blvd. will resume. Crews will be onsite to complete pavement restorations on Brookside Blvd. east of West 130th Street. During this period, Brookside Blvd. will be restricted to local traffic only, with no street parking permitted. Stay alert for changing traffic patterns and observe all posted speed limits.
UPDATE: As of 1/12/2024
Sewer construction on Brookside Blvd has been completed. The contractor will resume pavement restoration and tree lawn restoration in the spring.
Thank you,
End Date
Project Type
Sewer ProjectsProject Status
Completed
Brookside Blvd